Wednesday, June 1, 2011

Updates from 5/31, 5th Period

Milestones:
6/3: order all materials for delivery 6/8
6/6: start digging the irrigation stream and the location that will hold the underground cistern
6/8: spread the rock and gravel, and start painting the "Washington-Lee High School - Go Generals" rocks
6/10: done with the stream
6/13: dig holes for the plants
6/14: put the plants in the ground
6/16: FINISH THE PROJECT!

Today was very hot (32*C, 92* F, so we stayed inside and did some research on companies that could deliver materials like rock and boulders. We also got a message from Nancy and Hillary with Rainwater Harvesting Collection Systems, (www.rainxchange.com), with some advice regarding plants. We should start digging in a few days!